The Construction of Bagnell Dam: When It Happened

August 6, 1929 Construction Began

September 5, 1929 Clearing for Reservoir Started

September 30, 1929 Layout of Cofferdam (Spillway and West Abutment)

October 3, 1929 Excavation for East Abutment Started

October 11, 1929 Excavation for West Abutment Started

November 21, 1929 First Steel Setting on Osage Bridge

December 21, 1929 Temporary Power House Tested

April 9, 1930 First Concrete Poured

July 22, 1930 Diversion Channel Opened

August 5, 1930 Upstream Side of Cofferdam Closed

December 10, 1930 Power House Steel Structure Erection Started

January 31, 1931 Highway Slab Completed

February 2, 1931 Lake Began to Fill

May 20, 1931 Lake Reached Spillway Crest Elevation

May 30, 1931 Lake Traffic Began

August 6, 1931 Generator Tests Started

September 3, 1931 Water Wheel Tests Started

October 16, 1931 First Commercial Operation of Osage Plant

December 24, 1931 Lake Area Electric Service Began